Fort Mitchell Gateway at the Drawbridge Inn Site: Roads First

The sidewalk along Buttermilk Pike between Chamber Center Drive and the I-71/75 interchange is gone. Crews are adding a turn lane in front of the planned Fort Mitchell Gateway development, and the state says pedestrians can't be given access while the work is going on. According to WKRC Local 12, some walkers have been cutting through the construction zone, and others have been crossing five lanes of traffic where there's no crosswalk.

For anyone who has driven past the old Drawbridge Inn lot over the past decade, this is the first work there that changes a daily routine. It's also the clearest sign of how the project is being built. Crews are finishing the roads before any building goes up. The senior living community follows because its financing is lined up, while the shops and restaurants most neighbors are waiting for sit at the back of the line with the fewest details settled.

A Lot That Sat Empty for Over a Decade

The Drawbridge Inn closed in December 2012, and the buildings were torn down in April 2014. The first major plan was a $135 million mixed-use project that included a Christ Hospital surgery center. It stalled after St. Elizabeth opposed Christ's Certificate of Need, and the surgery center ended up in litigation. In January 2019, WVXU reported a revised plan with smaller buildings, a hotel, restaurants, retail and apartments in place of the surgery center.

A new development agreement came in 2023, with work expected to start by the end of that year. LINK nky reported the details at the time. The Kenton County Planning Commission approved the current Gateway plan in August 2024. The Northern Kentucky Port Authority describes it as a 26-acre redevelopment. The developer of record is Buttermilk Pike Development Company, and the partners are Brandicorp, Greenbrier Development, St. Elizabeth Healthcare and Perkins Eastman. LINK nky puts the total planned investment above $200 million, led by Bellevue-based Brandicorp LLC.

Over three versions of the plan, the hotel, the apartments and the surgery center have come and gone. The two pieces that held on are the medical offices and housing. Both are tied to St. Elizabeth.

Why Royal Drive Had to Move First

Nothing vertical can go up until the site has a road that can carry the traffic. Because the site sits right next to I-71/75, the state required a full traffic impact study. The approved plan removes Royal Drive, moves it and rebuilds it, with two inbound and five outbound lanes connecting to Buttermilk Pike. The 2023 plan also included a hard median on Buttermilk Pike, which the Kentucky Transportation Cabinet requested.

Here's how that work has gone so far:

  1. A section of Royal Drive closed on Dec. 13, 2024.
  2. By May 2026, the road structure was finished, sewer and road improvements were done, and utility work was still underway. City Administrative Officer Edwin King told LINK nky that crews "ran into some rock that they didn't expect."
  3. By mid-September, Royal Drive had reopened and was serving as the walking detour. WKRC reported that the detour adds an extra mile to what is normally a 10-minute walk, and the new road's sidewalk wasn't finished yet.
  4. The Buttermilk Pike turn lane is the current phase. It's the reason the sidewalk had to come out.

The Kentucky Transportation Cabinet explained it this way in a statement to WKRC:

"Work on the additional lane requires the Buttermilk Pike sidewalk be rebuilt between Chamber Center Drive and the I-71/75 interchange, and access cannot be provided for pedestrians during construction."

WKRC calls this part of Buttermilk Pike one of Northern Kentucky's busier corridors for people on foot and on bikes, because it connects to Dixie Highway and the TANK bus line there. On Sept. 16, the station reported the sidewalk might not reopen for another month or longer because of weather and utility issues. NKY Current followed up on Sept. 17 and didn't give a reopening date either. Check the signs on site before planning a walk that way.

The Ormsby Goes Up Next Because Its Money Is Lined Up

The first building is The Ormsby, a joint project of St. Elizabeth Healthcare and Dallas-based Greenbrier Development. LINK nky describes a seven-story senior community for residents 62 and older, with 203 units and a 48-bed health center. The name honors Maj. Gen. Ormsby MacKnight Mitchel, the same Civil War general the city is named for.

In late July, the city held a special meeting and approved an interlocal agreement with the Kentucky Bond Development Corporation, a nonprofit set up by the Kentucky League of Cities. The agreement lets the corporation issue tax-exempt bonds for The Ormsby. LINK nky reported that the bond issue is capped at $250 million. The project, not the city's general budget, repays bondholders, and Mayor Greg Pohlgeers said Fort Mitchell bears no financial liability. City Administrator Edwin King said the meeting was called because the city didn't want to delay the project. According to a public bond notice, the bond corporation's board passed its own resolution on Aug. 18, 2026, authorizing up to $250 million in revenue bonds to buy, build and equip the community.

The $250 million figure is a ceiling on borrowing that the project itself will repay. It isn't city money. The earlier deal terms point the same way. NKY Current reported earlier provisions for up to $120 million in bonds across three series, a $2 million Port Authority deposit for storm and sewer work, and a $2 million city commitment for street infrastructure. Most of the money already lined up is tied to The Ormsby and the roads, so those are the pieces moving first.

The ceremonial groundbreaking for The Ormsby happened on Nov. 1, 2024. Coverage at the time expected residents to move in by 2026. That date has slipped. As of May 2026, LINK nky reported that vertical construction was expected to start this fall, with building on both sides of Royal Drive once the remaining utility work wraps up. No new move-in date has been announced.

Piece of the Gateway What's public as of mid-October 2026 Timing on record
Royal Drive relocation Rebuilt and reopened; sidewalk unfinished in September Closed Dec. 13, 2024; reopened by mid-September 2026
Buttermilk Pike turn lane Underway; sidewalk removed from Chamber Center Dr. to I-71/75 No firm sidewalk reopening date
The Ormsby 203 units, 48-bed health center; up to $250M in bonds authorized Aug. 18 Vertical construction expected fall 2026
Two St. Elizabeth medical office buildings Part of the approved plan The 2023 plan put occupancy around 2029
Retail and restaurants No tenants or square footage announced None given

The Restaurants Are the Least Defined Part

The retail and restaurant space is the part neighbors ask about most, and it has the fewest details. NKY Current reported on Aug. 4 that retail and restaurant square footage, tenants and opening timelines hadn't been made public.

What has been described is the commercial pad itself. 2477 Royal Drive sits directly in front of The Ormsby and faces I-71/75, Buttermilk Pike, Royal Drive and Grace Avenue. LINK nky cites an average of 19,843 vehicles passing each day. The same report says the final uses will be shaped in part by the site's tax increment financing structure, which puts future tax revenue back into the upfront infrastructure.

Put simply, the restaurant pad sits in front of a seven-story building that isn't up yet, on a site whose tax revenue is helping pay for the roads now being built. Tenants usually sign on for a site like that once the traffic, the parking and the anchor building are visible. An engineering firm's profile of the project lists a grocery store among future phases. The newer descriptions from the Port Authority and local news don't mention one, so for now a grocery store is unconfirmed.

What to Watch on Buttermilk Pike Through Winter

Each of these would move the project to its next step:

  • The sidewalk reopening between Chamber Center Drive and I-71/75. This is the change that matters most for anyone walking to Dixie Highway or the TANK line.
  • Vertical work on The Ormsby. Cranes and steel would mean the Gateway has moved past roadwork.
  • A first named tenant for 2477 Royal Drive. Through August, none had been announced.
  • The interchange redesign. LINK nky reported in May that the state plans a double-diamond interchange at Buttermilk Pike to ease congestion. A construction date from KYTC would be the next milestone to look for.
  • City council minutes. The City of Fort Mitchell posts meeting minutes after they're approved at the following meeting, so Gateway decisions show up there a few weeks after the vote.

If you own a home near Buttermilk Pike and wonder how a project this size could affect your street, your commute or your home's value over the next few years, Martha Works Larsen follows the Gateway as closely as you do. Call or text Martha to schedule your free consultation. She'll walk you through what the plans show today and what to watch as each phase opens.

Work With Martha

Get assistance in determining current property value, crafting a competitive offer, writing and negotiating a contract, and much more. Contact me today.

Follow Me on Instagram